Site installs on the Logistics sheet
Site installs on the Logistics sheet
The Logistics sheet shows each project's install trips above the assets, and a booking can be tied to the site install it supports. You can see when a crew is on site, what is already booked for that install, and what is still missing, without leaving the sheet.
Open Logistics in the sidebar, or Time & Availability and then the Logistics tab, and stay on Schedule.

Site installs sit above the assets and use the same day columns.
Where the installs come from
Nothing is typed in twice. The section reads the install trips on each project's Work Plan: the rows marked as an install trip, with their Truck Pack and Site Install rows. Change a date on the Work Plan and the bar moves on the sheet.
- There is one row per project. A project gets a second row only when two of its trips share a day.
- The bar covers the days on site: the dates of the Site Install row. The truck pack, the travel and the rest days are not part of it.
- The number at the start of the bar is how many assets are booked for that install. A yellow 0 means nothing is booked for it yet.
- Click the project name to open the project. Click Site installs to fold the section away; the sheet remembers your choice.
- The search box filters installs by project code, project name or trip name, as well as assets.
Draft and cancelled projects are not listed. A project with no install trips on its Work Plan has no row.
Say what a booking is for
Click a free day on an asset row, as before. After you pick the project, the form shows What it is for. Pick one or more tasks of that project. The list offers the project's site installs first, then its other dated tasks, such as commissioning or first use.

- If the day you clicked falls on exactly one install, it is picked for you, and the form says so. You can remove it or add more.
- The tasks you pick set the window: the first day of the earliest one to the last day of the latest one. For an install, that is its days on site.
- A booking can also be for nothing. Leave the list empty for training, maintenance, a loaner or a service call.
Buffer days
When you pick what a booking is for, its days are set to the window plus 5 days before and 5 days after, for prep, pack and shipping. Change either number on the form, or type the dates yourself.
- On the sheet, buffer days are drawn lighter than the days of the window.
- The hover on a booking says what it is for and how many buffer days it has.
- When the window moves, the buffer moves with it.
Leave an asset on site
Tick Leave on site when the asset does not come back at the end of the window, for example carts that stay between two installs. Then choose until when:
- No return date yet: the booking has no end. It holds the asset until somebody sets a return date.
- A return date: type the end date.
- The end of another task: the booking ends when that task ends, and follows it if it moves.
Days after the window are drawn striped while the asset is left on site. To set the return date later, click the booking, change Until and press Save. The same form lets you change the days and what the booking is for.
Start from the install
Click an install bar to open it. You see the days on site, the truck pack day, and two lists.

- Booked for this install: every asset tied to it. Untie removes the tie and keeps the booking.
- On these days for this project, tied to no install: bookings for the same project that overlap the install but were never tied to it. Use Tie to this install on one, or Tie all.
- Book an asset for it: closes the panel and shows a reminder above the sheet. Click a free day on any asset row and the form opens with the project and the install already filled in, through the last day on site. Press Done on the reminder when you have finished.
See what belongs together
- Hover an install: its bookings are outlined on the asset rows, and the tip lists them.
- Hover a booking: its install is outlined, and the tip shows Site install with the trip name and dates. If the project has installs and the booking is tied to none, the tip says Not tied to one.
- Click a booking to open its details. Site install is a picker there too, so you can move a booking to another install or untie it.
Asset requests
When someone uses Request asset on an install trip in the Work Plan (the trip itself, its Site Install row or its Truck Pack row), the request remembers the trip. When a coordinator presses Schedule on it, the booking is tied to that install automatically, and the form says which install before you confirm. A request made on any other task is tied to an install only if its dates fall on exactly one.
More on requests: Asset requests and approvals.
See an install's assets on the Work Plan
The Work Plan row of an install trip carries an Assets chip. It counts everything for that install: the requests made on the trip, its Site Install row or its Truck Pack row, and every booking tied to the install on the Logistics sheet.

- Hover the chip to read each asset with its days. Awaiting approval is a request that has not been scheduled yet. Approved is an asset that is booked.
- Once a request is scheduled, its chip shows the days that were booked, which can differ from the days that were asked for.
- If the booking made from a request is removed, the request goes back to the Logistics inbox.
- The chips are shown to the people who can open the Logistics inbox: owners, admins, managers and members who hold the Logistics coordinator permission.
When an install moves
The assets booked for an install move with it. When the dates of an install change, or of any task a booking is for, each booking keeps its place: an asset booked for the whole window covers the whole new window, a delivery before it stays the same number of days before it, and a pickup at the end stays at the end.
- The person who moves the install sees a short message naming the assets that moved.
- A move made outside the Work Plan is caught within a few minutes.
An asset does not move when it is booked for another project on the new days. That is a clash, and a person decides:

- Unlink it from this install. The booking keeps its days and is no longer tied to the install.
- Swap the later booking to another asset. Of the two bookings that clash, the later one gets another free asset of the same kind. The list only offers assets that are free.
- Cancel the later booking. It is marked cancelled so a new plan can be made. A cancelled booking no longer holds its asset.
- Keep it tied on its old days, or Decide later.
Until someone decides, the install's chip on the Work Plan reads Check dates, the Logistics sheet says how many bookings need a check, and the people who schedule logistics are notified once.

Requests that have not been scheduled yet follow the install as well.
Freight
The Freight section is the first group of assets on the sheet. It has one lane for each project with a shipment in the window, named after the project.
Directions are read from your side: Outbound is a shipment leaving for the site, Inbound is one coming back. The days between the day it ships and the day it arrives are shown lighter.

- Press + Shipment, or click a free day on a project's lane, to add a shipment.
- Pick the site install and the direction. An outbound shipment defaults to 3 days before the first day on site, an inbound one to the last day. You can change the dates, and add a time of day to each if you know it.
- Pick the project by typing its number or its name. The list is in number order.
- Choose the freight method and the route: an origin, a destination, and more stops with + Add a stop. Outbound starts as your first named location to the jobsite; inbound is the reverse. A stop can also be Other project: pick the project and its site address is filled in.
- Booking details are optional: carrier, broker, driver name, driver phone and PRO number. They show in the hover and on the project's Itinerary.
- The dot on a shipment is red until an Itinerary booking is picked on it from the project's list, then green.
- It works from the Work Plan too: type a task named Freight, give it a date and no hours, and it appears on the sheet as a shipment. Name it "Freight - inbound" for a shipment back from the site.
- Jobsite in a route is the project's address. It shows in the hover and in the shipment form.
- Each shipment is also a task named Freight on the project's Work Plan. Change the date in either place.
- A shipment tied to an install moves with the install.

Default shipments gives every upcoming install its outbound and its inbound shipment in one step. It first says how many it would add. Installs that already have theirs are left alone, and a default shipment you remove is not added again.
An organization admin can press Options to edit the list of freight methods and the named locations, and to have new installs get their two shipments automatically.
Freight on the Itinerary
A project's Itinerary has a Freight panel that lists its shipments: direction, days and times, method, status, route and booking details. Edit and + Shipment open the same form as the sheet, so a change made in either place shows in both.
From the sheet, an install's card has + Shipment for that install and a link to the project's Itinerary.
Choose how much you see
The sheet opens on the next 6 weeks, one column per day. The window menu also offers the next 4 weeks, a calendar month, or the next 12 weeks, which is drawn with one column per week, starting on Monday. Each week shows the booking that holds most of it, and a small +1 when another booking shares that week. Click a week to open its booking.
Move a booking by dragging
Drag a booking or a shipment to another day of its own row. It keeps its length and stays tied to its install.
- If the asset is already booked on the new days, nothing moves and a message says who has it.
- In the 12-week view, one column moves it one week.
- Dates can still be changed on the form.
Put the rows in your order
Point at a row and drag the small grip at its left edge up or down. A line shows where the row will land. Rows move inside their own section (Site installs, Freight, Fleet and so on), and the order is saved for your whole organization. A new asset or project takes its usual place after the rows you arranged.
Each section folds from its heading, and an asset row shows the asset's name only. Hover the name for its details.
Who can book
Booking, changing and removing assets and freight shipments on the Logistics sheet is for:
- owners, admins and managers,
- anyone an admin has made a Logistics coordinator,
- anyone listed as the project manager of a project.
Everyone else can still see the sheet. For them, a click on a free day opens Request asset, which sends the request to the people who schedule logistics.
Good to know
- Tying or untying a booking never changes its dates and never changes the Work Plan.
- If an install trip's dates move, its bookings move with it. Only a booking that clashes with another project stays put and is flagged Check dates.
- If an install trip is deleted from the Work Plan, its bookings stay on the sheet and show as not tied to an install.
- Bookings made before this feature are not tied to anything. Open each install and use Tie all to catch them up.
- If an asset stays out for two trips, pick both installs under What it is for, or tick Leave on site.
Example: get the truck and carts on one install
Find the project in Site installs and click its bar. The panel shows one truck booked and two cart sets on the same days that are tied to nothing. Press Tie all. Then press Book an asset for it, click a free day on the test kit's row, and press Book. The number on the bar now reads 4, and hovering the bar outlines all four bookings.
Related: Logistics Schedule.