Labor estimate on the Work Plan

Labor estimate on the Work Plan

A job can carry a stored labor estimate: hours, crew, and days by team. That table is the sold-order receipt. It is not the same as the EST cell on a task row, and it is not the hours you have already booked.

Open the card

On Work Plan:

  • Hover or click the Hrs (sch/est) column header.
  • Or click the clipboard icon in the Work Plan header (with Expand / Collapse). The icon is hidden when the job has no stored estimate.

The card lists each team on one row. There is no inner scrollbar.

Shift-click Hrs (sch/est) still sorts the grid by estimate. A plain click opens the card when an estimate exists. If there is none, a plain click sorts as before.

After you have sorted, click WBS to return to outline order.

What the card shows

  • Estimate — hours on the stored receipt
  • Work Plan — EST hours on the live task tree (leaf tasks only)
  • Crew and Days from the receipt
  • Delta — how far Work Plan is from the estimate

An unmapped role is labeled, not guessed. It does not create demand.

What ±10% means

The Hrs header and the clipboard icon highlight when Work Plan EST is 10% over or under the stored estimate — on the total, or on a team. That is a warn line, not a lock. You can still edit hours.

A checkup sends one Slack notice for the jobs that just crossed that line — not one message per job, and not on every page load. Opening the Work Plan does not send the notice again.

Hrs on the row

The column is scheduled hours over the task estimate. Requested team hours (nobody booked yet) show in italic — the same number as the assignment panel. Parent Hrs add the children. You edit EST on a leaf, not on a parent.

Saving EST on a task cell scales unbooked team requests in proportion and keeps the current split. A person already booked on the task is left alone.

Use Match requests to EST on the toolbar to do the same for checked rows. A parent (including a trip parent) includes its children. Nothing checked asks whether to flow the whole project, then confirms again. Tasks with a person booked are skipped. That change cannot be undone from the button — check the rows first.